Removal Procedure
Sectioning is performed on the lower front hinge pillar between the
2 hinge mounting locations. The hinge pillar inner reinforcement on
the service part is used as a backing plate when welding the new section
in place.
- Remove all of the related panels and the components.
- Visually inspect and restore as much of the damage as possible
according to factory specifications.
- Remove the following components:
• | The corrosion materials |
- Drill out and remove the
access panel (1) located on the upper, outer rail reinforcement.
- Cut and pry the outer
reinforcement away from the hinge pillar as necessary in order to provide
room for the sectioning template.
- Align the template that was provided with the service part. Mark
a line where indicated.
- Cut the hinge pillar and inner reinforcement along the line.
- Perform additional sectioning procedures as necessary in order
to remove damaged areas of the door frame opening.
- Locate and mark factory welds. Note the number and location for
installation of the service part.
- Notice the number of welds for installation of the service part.
- Remove the damaged section of the door frame opening and the hinge
pillar inner reinforcement.
- Drill out the 4 welds attaching the hinge pillar to the
inner reinforcement above the cut line.
- Remove the remaining section of the inner reinforcement.
Installation Procedure
- Align the template on
the service part and mark a cut line where indicated.
Important: Only cut the outer surface of the hinge pillar service part. The inner
reinforcement is used as a backing plate when installing the new section.
- Cut the service part along the marked line. Do not damage the hinge
pillar inner reinforcement.
- Drill out the 4 welds attaching the hinge pillar to the inner
reinforcement above the cut line. Do not drill through the inner reinforcement.
- Perform additional sectioning procedures as necessary to remove
the unused areas of the service part including the access panel (1)
located on the upper, outer rail reinforcement.
- Drill 8 mm (5/16 in) plug weld holes as necessary
in the locations noted from the original section.
- Prepare all mating surfaces for welding.
Important: Prior to refinishing, refer to the publication GM 4901M-2000
"GM Approved Refinish Materials" for recommended products. Do
not combine paint systems. Refer to paint manufacturer's recommendations.
- Position the door frame opening service part. Make sure the inner
reinforcement extending from the top of the hinge pillar service part is properly
positioned within the existing hinge pillar section.
Important: To ensure a secure weld, the hinge pillar sectioning joint should have
a gap of approximately one -and-one-half times the thickness of the
metal. Trim the parts as necessary to achieve this.
- Check fit using body dimensions and plug weld accordingly with frequent
measurements to ensure proper fit.